铁路系统给水施工中存在的问题及预防措施
郭佩佩
【摘 要】给水施工是工程建设的重要组成部分,作为铁路给水系统,给水工程施工的好坏直接影响到路内单位的生产、消防用水以及居民的生活用水,同时影响给水系统的正常运行。因此必须严格把好给水工程施工质量关。文章结合给水施工现场及管理的实践,分析了给水施工中存在的问题,提出了一些解决工程实际问题的具体措施。
【Abstract】Water supply construction is an important part of engineering construction. As the railway water supply system, the construction quality of water supply engineering directly affects the production of the units of the bureau, fire water and living water, and affects the normal operation of the water supply system. Therefore, the construction quality of good water supply must be strictly controlled. Based on the practice of field construction and management of water supply, this paper analyzes the existing problems in the water supply construction and puts forward some concrete measures to solve the practical problems.
【關键词】铁路系统;给水施工; 存在问题;预防措施
【Keywords】 railway system; construction of water supply; existing problems; preventive measures
【中图分类号】U215 【文献标志码】A 【文章编号】1673-1069(2017)09-0175-02
1 引言
给水工程是工程建设的重要组成部分,作为铁路给水系统,其施工的复杂性和安全性更为突出。大部分给水管道沿铁路沿线铺设,对于我车间管辖范围内给水管道来说,是围绕郑州北站地区铺设的环状供水管网。不仅有铺设在铁路股道中间的给水管道,还有穿越股道的给水管道,且站区内大部分给水管道都是沿铁路线外铺设。对于这些给水管道的更新改造,或者接引给水管道到室外新建的铁路沿线房屋建筑,除了要按照国家规范标准进行给水施工,还要严格按照铁路(邻近)营业线施工进行组织安排。给水工程施工的好坏直接影响到路内单位的生产、消防用水,对于有客车上水的站区,同时影响到客车上水,给旅客造成极大不便。因此必须严格把好给水工程施工质量这一关。论文结合给水施工现场及管理的实践,分析了给水施工中存在的问题,提出了一些解决工程实际问题的具体措施。
目前铁路给水施工主要存在两大方面的问题:一是施工现场的安全问题;二是施工作业的质量问题。
2 施工现场安全问题
安全管理不到位 。施工前各配合单位没有及时召开施工协调会,施工期间没有到或很少到施工现场检查指导,造成很多违章作业或后期返工现象;施工前的安全教育以及施工中各项安全措施没有得到具体落实;施工现场缺乏检查指导,造成违章作业;施工单位没有形成完善的安全管理体系,没有严格依照安全管理施工规范要求约束作业人员,造成人员作业安全隐患,增加了施工风险;(邻近)营业线施工未按照要求进行安全协议的签订、施工安全组织技术措施的审核、对外用工人员的培训考试、开工许可证的办理、高风险作业票的签发、施工前预备会、日安全教育、施工总结会的召开,造成作业人员职责不明、作业范围不清,防护人员干与工作无关的事,没有和驻站联络员严格执行呼叫联络制度,造成严重的安全隐患。
3 施工作业质量问题
3.1 管材质量问题
投标单位为了中标,报价低,生产产品时忽视工程质量,片面压低造价,导致施工单位购买劣质产品,造成管路打压试验时或后期使用中发生断裂、漏水情况;或管材生产批次不一,购买时作为一批次发货,造成管材之间连接出现问题,容易发生接口漏水情况。
3.2 施工工艺不规范
施工流程有误、施工程序不规范,管道安装施工与其它建筑施工一样,有着内在的规律性,这就要求施工时严格按科学的程序进行,防止随意性和盲目性,如管道的安装,如果前后顺序颠倒,就会使管道无法进入预定的位置。如管沟开挖、作业坑开挖不合标准,造成作业人员操作困难,管道连接出现问题;PE管接口未擦拭干净、热熔连接压力不合适、温度过高、冷却时间过短,都会造成管道接口漏水;管道打压试验回填覆土厚度不够,容易造成打压失败、管道断裂等。
3.3 人员技术水平不高
在给水施工存在的问题中,因施工技术水平不高,造成质量问题的占很大比例。很多技术工人,连起码的施工工艺都不懂,就在一线施工;有些施工技术人员,没有施工经验,甚至连图纸都吃不透,就独挡一面;一些监理人员未经培训就上岗,直接影响了给水工程的质量。更有对新技术、新设备、新工艺不熟悉就直接凭经验操作,造成施工问题。
3.4 二次污染现象
由于铁路供水体制的原因,为了满足高峰期单位和居民用水,增加了储水池等中间环节,增大了水质污染的可能性。传统的钢筋混凝土水池由于表面粗糙,极易滋生青苔、微生物、细菌;水池检修孔、溢流管等附件极易封闭不严造成水质污染。有资料显示,水在水箱中贮存24h后余氯为零,超过24h后,水质会严重恶化,而生活消防合用水池中水的停留时间大都超过24h。
4 预防措施
4.1 施工安全问题的预防措施
在铁路沿线进行给水施工作业中,要严格遵守铁路(邻近)营业线施工相关要求,按照施工流程进行手续办理和作业前的准备工作。首先和相关站段签订施工安全协议,同时编制施工安全技术组织措施,待审核通过后,办理开工许可证。对存在劳务用工的施工作业,提前对劳务工做好安全教育和培训工作,待考试合格后方可上岗,且必须有路工带领方能进入作业区域。在施工作业开始前,各单位之间组织开施工协调会。施工单位组织作业人员和防护人员、驻站联络员一起召开施工预备会,明确施工作业范围和次日施工内容,明确各人岗位分工和职责。做好每日职工的安全教育工作,对当日施工结束后召开施工总结会,对本日施工情况进行总结,对发现的问题提出整改措施。对存在高风险作业内容的施工,按时签发高风险作业票,要求职工对作业中存在的安全风险点及防范措施做到心中有数,施工作业中时刻保持清醒的头脑,做好自控、互控、他控,避免碰、砸、挤、压等惯性事故的发生。
4.2 施工质量问题的预防措施
4.2.1 管材质量预防措施
施工中使用的管材和配件必须有生产单位出具的合格证明、材料检验报告、企业资质等材料,承压不小于1MPa;施工前必须对使用的管材进行材質检查。给水管道铺设、给水附件件安装、阀门安装和管沟开挖及回填、水压试验、管道冲洗和消毒,严格按照TB10209-2002《给水施工规范标准》要求执行。
4.2.2 施工工艺问题的预防措施
①管沟开挖及回填注意事项。管沟开挖应以“当天开挖、当天铺设、当天回填”为原则,管槽开挖以直线为宜,人工开挖管槽时,要求沟槽底部平整、密实,无尖锐物体。沟底可以有起伏,但必须平滑地支撑管材,若有超挖时,必须回填夯实。回填必须从管两侧同时回填,回填一层夯实一层。防止槽内积水造成管道漂浮。②PE管铺设注意事项。PE管材在焊接前,必须清洁加热板、模头表面及管材焊接端面,以免有杂质造成接口连接问题,造成漏水;PE管焊接温度不应过高,PE管道焊接温度一般为200℃~240℃;夏天给水PE管道安装完毕后,由于管材曝晒在阳光下,吸收热量,使管材内试压水温度迅速升高,建议选择气温相对较低的早晨进行试压;管道试压前,一般情况下回填土不宜少于500mm;管道试压后的大面积回填,宜在管道内充满水的情况下进行,管道敷设后不宜长时间处于空管状态。
4.2.3 人员业务水平提升
铁路供水单位目前存在职工老龄化严重的现象,职工普遍存在年纪大、记忆力不好,对学习教育存在畏难情绪。在实际工作中,可以采取对文件精简后进行传达。组织职工进行安全警示教育,吸取安全事故教训。做好职工安全教育培训,使职工对本岗位的安全风险点及防范措施熟悉。同时做好业务学习教育,坚持每日班前一题,每周业务学习,每月岗位练兵,认真对待每次岗位练兵,做到学习练兵有收获,做到本工种应知应会,必知必会烂熟于心。还要通过各方面积极宣传,形成氛围,使职工从思想上转变,从“要我学”转为“我要学”,形成人人不甘落后,与时俱进,不断接受新事物,学习新技术、新设备、新工艺,提升素质水平和业务技能。
4.2.4 水质问题的预防措施
对于铁路供水单位来说,主要做到汛期防止雨水倒灌,防止发生水质污染现象。做到汛期密切关注天气预报,以雨为令,做好雨前,雨中、雨后设备和无人值守泵房巡检工作。恶劣天气,加强巡检,一旦发现问题,及时反馈。对采取二次加压储配水设备。如水池水塔等做好清洗,按检修计划对其进行彻底清洗,同时保证消毒设备的正常运行。确保管网出水余氯含量0.3以上。
【摘 要】给水施工是工程建设的重要组成部分,作为铁路给水系统,给水工程施工的好坏直接影响到路内单位的生产、消防用水以及居民的生活用水,同时影响给水系统的正常运行。因此必须严格把好给水工程施工质量关。文章结合给水施工现场及管理的实践,分析了给水施工中存在的问题,提出了一些解决工程实际问题的具体措施。
【Abstract】Water supply construction is an important part of engineering construction. As the railway water supply system, the construction quality of water supply engineering directly affects the production of the units of the bureau, fire water and living water, and affects the normal operation of the water supply system. Therefore, the construction quality of good water supply must be strictly controlled. Based on the practice of field construction and management of water supply, this paper analyzes the existing problems in the water supply construction and puts forward some concrete measures to solve the practical problems.
【關键词】铁路系统;给水施工; 存在问题;预防措施
【Keywords】 railway system; construction of water supply; existing problems; preventive measures
【中图分类号】U215 【文献标志码】A 【文章编号】1673-1069(2017)09-0175-02
1 引言
给水工程是工程建设的重要组成部分,作为铁路给水系统,其施工的复杂性和安全性更为突出。大部分给水管道沿铁路沿线铺设,对于我车间管辖范围内给水管道来说,是围绕郑州北站地区铺设的环状供水管网。不仅有铺设在铁路股道中间的给水管道,还有穿越股道的给水管道,且站区内大部分给水管道都是沿铁路线外铺设。对于这些给水管道的更新改造,或者接引给水管道到室外新建的铁路沿线房屋建筑,除了要按照国家规范标准进行给水施工,还要严格按照铁路(邻近)营业线施工进行组织安排。给水工程施工的好坏直接影响到路内单位的生产、消防用水,对于有客车上水的站区,同时影响到客车上水,给旅客造成极大不便。因此必须严格把好给水工程施工质量这一关。论文结合给水施工现场及管理的实践,分析了给水施工中存在的问题,提出了一些解决工程实际问题的具体措施。
目前铁路给水施工主要存在两大方面的问题:一是施工现场的安全问题;二是施工作业的质量问题。
2 施工现场安全问题
安全管理不到位 。施工前各配合单位没有及时召开施工协调会,施工期间没有到或很少到施工现场检查指导,造成很多违章作业或后期返工现象;施工前的安全教育以及施工中各项安全措施没有得到具体落实;施工现场缺乏检查指导,造成违章作业;施工单位没有形成完善的安全管理体系,没有严格依照安全管理施工规范要求约束作业人员,造成人员作业安全隐患,增加了施工风险;(邻近)营业线施工未按照要求进行安全协议的签订、施工安全组织技术措施的审核、对外用工人员的培训考试、开工许可证的办理、高风险作业票的签发、施工前预备会、日安全教育、施工总结会的召开,造成作业人员职责不明、作业范围不清,防护人员干与工作无关的事,没有和驻站联络员严格执行呼叫联络制度,造成严重的安全隐患。
3 施工作业质量问题
3.1 管材质量问题
投标单位为了中标,报价低,生产产品时忽视工程质量,片面压低造价,导致施工单位购买劣质产品,造成管路打压试验时或后期使用中发生断裂、漏水情况;或管材生产批次不一,购买时作为一批次发货,造成管材之间连接出现问题,容易发生接口漏水情况。
3.2 施工工艺不规范
施工流程有误、施工程序不规范,管道安装施工与其它建筑施工一样,有着内在的规律性,这就要求施工时严格按科学的程序进行,防止随意性和盲目性,如管道的安装,如果前后顺序颠倒,就会使管道无法进入预定的位置。如管沟开挖、作业坑开挖不合标准,造成作业人员操作困难,管道连接出现问题;PE管接口未擦拭干净、热熔连接压力不合适、温度过高、冷却时间过短,都会造成管道接口漏水;管道打压试验回填覆土厚度不够,容易造成打压失败、管道断裂等。
3.3 人员技术水平不高
在给水施工存在的问题中,因施工技术水平不高,造成质量问题的占很大比例。很多技术工人,连起码的施工工艺都不懂,就在一线施工;有些施工技术人员,没有施工经验,甚至连图纸都吃不透,就独挡一面;一些监理人员未经培训就上岗,直接影响了给水工程的质量。更有对新技术、新设备、新工艺不熟悉就直接凭经验操作,造成施工问题。
3.4 二次污染现象
由于铁路供水体制的原因,为了满足高峰期单位和居民用水,增加了储水池等中间环节,增大了水质污染的可能性。传统的钢筋混凝土水池由于表面粗糙,极易滋生青苔、微生物、细菌;水池检修孔、溢流管等附件极易封闭不严造成水质污染。有资料显示,水在水箱中贮存24h后余氯为零,超过24h后,水质会严重恶化,而生活消防合用水池中水的停留时间大都超过24h。
4 预防措施
4.1 施工安全问题的预防措施
在铁路沿线进行给水施工作业中,要严格遵守铁路(邻近)营业线施工相关要求,按照施工流程进行手续办理和作业前的准备工作。首先和相关站段签订施工安全协议,同时编制施工安全技术组织措施,待审核通过后,办理开工许可证。对存在劳务用工的施工作业,提前对劳务工做好安全教育和培训工作,待考试合格后方可上岗,且必须有路工带领方能进入作业区域。在施工作业开始前,各单位之间组织开施工协调会。施工单位组织作业人员和防护人员、驻站联络员一起召开施工预备会,明确施工作业范围和次日施工内容,明确各人岗位分工和职责。做好每日职工的安全教育工作,对当日施工结束后召开施工总结会,对本日施工情况进行总结,对发现的问题提出整改措施。对存在高风险作业内容的施工,按时签发高风险作业票,要求职工对作业中存在的安全风险点及防范措施做到心中有数,施工作业中时刻保持清醒的头脑,做好自控、互控、他控,避免碰、砸、挤、压等惯性事故的发生。
4.2 施工质量问题的预防措施
4.2.1 管材质量预防措施
施工中使用的管材和配件必须有生产单位出具的合格证明、材料检验报告、企业资质等材料,承压不小于1MPa;施工前必须对使用的管材进行材質检查。给水管道铺设、给水附件件安装、阀门安装和管沟开挖及回填、水压试验、管道冲洗和消毒,严格按照TB10209-2002《给水施工规范标准》要求执行。
4.2.2 施工工艺问题的预防措施
①管沟开挖及回填注意事项。管沟开挖应以“当天开挖、当天铺设、当天回填”为原则,管槽开挖以直线为宜,人工开挖管槽时,要求沟槽底部平整、密实,无尖锐物体。沟底可以有起伏,但必须平滑地支撑管材,若有超挖时,必须回填夯实。回填必须从管两侧同时回填,回填一层夯实一层。防止槽内积水造成管道漂浮。②PE管铺设注意事项。PE管材在焊接前,必须清洁加热板、模头表面及管材焊接端面,以免有杂质造成接口连接问题,造成漏水;PE管焊接温度不应过高,PE管道焊接温度一般为200℃~240℃;夏天给水PE管道安装完毕后,由于管材曝晒在阳光下,吸收热量,使管材内试压水温度迅速升高,建议选择气温相对较低的早晨进行试压;管道试压前,一般情况下回填土不宜少于500mm;管道试压后的大面积回填,宜在管道内充满水的情况下进行,管道敷设后不宜长时间处于空管状态。
4.2.3 人员业务水平提升
铁路供水单位目前存在职工老龄化严重的现象,职工普遍存在年纪大、记忆力不好,对学习教育存在畏难情绪。在实际工作中,可以采取对文件精简后进行传达。组织职工进行安全警示教育,吸取安全事故教训。做好职工安全教育培训,使职工对本岗位的安全风险点及防范措施熟悉。同时做好业务学习教育,坚持每日班前一题,每周业务学习,每月岗位练兵,认真对待每次岗位练兵,做到学习练兵有收获,做到本工种应知应会,必知必会烂熟于心。还要通过各方面积极宣传,形成氛围,使职工从思想上转变,从“要我学”转为“我要学”,形成人人不甘落后,与时俱进,不断接受新事物,学习新技术、新设备、新工艺,提升素质水平和业务技能。
4.2.4 水质问题的预防措施
对于铁路供水单位来说,主要做到汛期防止雨水倒灌,防止发生水质污染现象。做到汛期密切关注天气预报,以雨为令,做好雨前,雨中、雨后设备和无人值守泵房巡检工作。恶劣天气,加强巡检,一旦发现问题,及时反馈。对采取二次加压储配水设备。如水池水塔等做好清洗,按检修计划对其进行彻底清洗,同时保证消毒设备的正常运行。确保管网出水余氯含量0.3以上。