国内某220kV变电站噪声计税及降噪措施方案研究
摘要:本文介绍了《中华人民共和国环境保护税法》中关于噪声税的征收要求,并结合国内某220kV变电站出现厂界超标现象及应缴纳噪声税的情况进行了分析,并对可采取的降噪措施进行了研究,为今后220kV变电站规划及噪声治理提供了参考依据。
关键词:《中华人民共和国环境保护税法》;噪声税;噪声治理
中图分类号:X707 文献标识码:A 文章编号:2095-672X(2018)01-0004-02
DOI:10.16647/j.cnki.cn15-1369/X.2018.01.002
Research on noise taxation and noise reduction measures of a 220kV substation in China
Du Le
(Inner Mongolia Electric Power Survey and Design Institute Limited liability company,Hohhot 010020, China)
Abstract: This article introduces “Environmental protection law of the peoples Republic of China” about Requirements for noise tax collection, Combined with a domestic 220kV substation the phenomenon of exceeding the limits and the noise tax should be paid , Also studied the available noise reduction measures , It provides reference for planning and noise control of 220kV substation in the future.
Key words: Environmental protection law of the peoples Republic of China;Noise tax ;Noise abatement
即將于2018年1月1日起实施的《中华人民共和国环境保护税法》正式将噪声纳入到应税污染物的范围中,这也意味着过去按照《排污费征收标准管理办法》征收的噪声超标排污费将退出历史舞台[1]。2016年,全国各级环保部门共收到环境噪声投诉52.2万件,办结率为99.1 %。其中,工业噪声类占10.3 %,建筑施工噪声类占50.1 %,社会生活噪声类占36.6 %,交通运输噪声类占3.0 %[2]。由此看见,环境噪声投诉量占环境投诉总量的43.9%,已成为公众反映强烈的环境问题之一,而征收噪声税也成为治理噪声污染的一个重要手段。
1 环境保护税法关于噪声的税额标准
根据《中华人民共和国环境保护税法》的规定,工业噪声税额是按照超标分贝值来计算,共划分为6个等级:超标1~3分贝,每月税额为350元;超标4~6分贝,每月税额为700元;超标7~9分贝,每月税额为1400元;超标10~12分贝,每月税额为2100元;超标10~12分贝,每月税额为2800元;超标13~15分贝,每月税额为5600元;超标16分贝以上,每月税额为11200元,具体征税要求见下表。
2 国内某220kV变电站规划及布置
2.1 变电站规划及现状
变电站远期规划建设3台容量180MVA主变压器,全站按220kV、110kV、10kV三级电压设置,220kV规划出线4回;110kV规划出线12回; 10kV规划出线16回。
变电站现已建设2台容量180MVA主变压器 220kV出线2回;110kV出线1回;10kV出线16回。两台主变10kV侧各装设3×8Mvar的电容器。
本期工程建设1台180MVA变压器(3号主变)。
2.2 变电站平面布置情况
变电站平面布置呈刀把形,东西长110.5m,南北宽118.4m,围墙内面积1.245hm2,现状站区围墙高度2.3m。
变电站新建时由于工程建设用地指标紧张,因此总平面布置采用紧凑式布置方案压缩用地指标,使3号主变距离站区西侧围墙最近距离为9.4m,因此本期工程3号主变扩建完成后,导致站区西侧围墙出现噪声超标现象。
3 噪声控制设计方案
3.1 噪声排放执行标准
3.2 噪声影响预测分析
3.2.1 源强分析
本工程扩建工程完成后主要噪声源强为1号主变、2号主变、3号主变,源强情况见下表。
3.2.2 预测方法
预测方法:建立坐标系,确定各声源坐标和预测点坐标,并根据声源性质以及预测点和声源之间的距离等情况,按最不利情况考虑,将变电站3个主变简化为3个体源,只考虑厂界处围墙的隔声作用,计算出噪声从各声源传播到预测点的声衰减量,由此计算出各声源作用在预测点噪声的叠加值。
预测软件:soundplan。
建模情况:按最不利情况,源强按体源考虑。
3.2.3 噪声影响预测
本工程建成后,站内源强增加,厂界只有围墙情况下进行预测计算时预测结果为:本期工程扩建后,变电站厂界本次扩建主变一侧(变电站的西侧)预测值为53dB(A),南侧厂界预测值为48dB(A),北侧厂界预测值为48dB(A),东侧厂界预测值为46dB(A),西侧厂界噪声值超过《工业企业厂界环境噪声排放标准》(GB12348-2008)中2类标准中夜间50dB(A)的要求,最大超标值为3 dB(A),其余厂界均满足标准。
厂界只有围墙隔声情况下噪声预测等值线预测见图2。
3.2.4 噪声超标经济损益分析
变电站若按照原规划建设,则西侧厂界噪声昼间达标,夜间超过《工业企业厂界环境噪声排放标准》(GB12348-2008)中2类标准夜间50dB(A)的要求,夜间最大超标3 dB(A),根据《中华人民共和国环境保护税法》的规定,变电站为连续不间断运行方式,不涉及减半计算应纳税额情况,西侧厂界噪声昼间达标,夜间不达标,因此不累计计征噪声税,按照表1规定,超标1~3分贝,每月纳税额为350元/月,年纳税额为4200元/年,变电站一般设计寿命为40年左右,则设计寿命年内应纳税额为16.8万元。
3.3 噪声治理措施
变电站专项降噪措施分为隔声、消声、吸声和隔振等,根据噪声源具体情况选取适当的降噪措施,对于本工程,降噪措施主要考虑声源控制和隔声措施。
3.3.1 声源控制
本工程只考虑站区围墙的隔声作用时,经模式预测计算,如实现厂界达标,主变压器噪声水平应低于下表中所列数值。
主变压器出厂时,设备制造厂家须完成出厂噪声检测,提供检测报告。报告应包括如下内容:被检测设备的相关参数(型号、尺寸等)、测点分布图、测试时设备所處的工况、测试前后背景噪声情况、被测设备所处的环境(四周距离墙壁等障碍物的距离)、空载噪声测试值、短路噪声测试值、满负荷运行噪声保证值、辐射声功率级。
3.3.2 主变围墙侧增设防火墙
变电站扩建主变后,根据站区内平面布置情况,在扩建3号主变西侧2.34m处增设防火墙一道,新建防火墙长14.44m、高7.5m(与1号、2号现有防火墙长度一致),墙体及墙体表面应采用吸声材料,进一步提高降噪效果。增加防火墙后,建模预测本期扩建主变侧围墙的西侧厂界噪声值为50dB(A),达到《工业企业厂界环境噪声排放标准》(GB12348-2008)中2类标准昼间60dB(A)、夜间50dB(A)要求。
扩建主变围墙侧增设防火墙噪声预测等值线见附图3。
4 结论
本文通过对即将实施的《中华人民共和国环境保护税法》中关于噪声税的征收要求介绍,结合对国内某220kV变电站前期规划未考虑后期扩建工程高噪声设备布置情况,致使厂界噪声出现超标现象及应缴纳噪声税的情况进行了分析,对可采取的降噪措施进行了研究,为今后220kV变电站规划及噪声治理提供了参考依据。
参考文献
[1]尚风科技.环保税即将开征,你知道企业噪声税怎么计算吗?[EB/OL].http://dy.163.com/v2/article/detail/CV229SC40518 MEKF.html.2017-09-23/2017-11-7.
[2]中华人民共和国环境保护部. 中国环境噪声污染防治报告[R].北京:中华人民共和国环境保护部, 2017. 1-1.
[3] GB12348-2008, 工业企业厂界环境噪声排放标准[S].
[4] DL/T1518-2016, 变电站噪声控制技术导则[S].
收稿日期:2017-11-08
作者简介:杜乐(1984-),男,大学本科,工程师,研究方向为火电厂及输变电工程环境影响评价。
关键词:《中华人民共和国环境保护税法》;噪声税;噪声治理
中图分类号:X707 文献标识码:A 文章编号:2095-672X(2018)01-0004-02
DOI:10.16647/j.cnki.cn15-1369/X.2018.01.002
Research on noise taxation and noise reduction measures of a 220kV substation in China
Du Le
(Inner Mongolia Electric Power Survey and Design Institute Limited liability company,Hohhot 010020, China)
Abstract: This article introduces “Environmental protection law of the peoples Republic of China” about Requirements for noise tax collection, Combined with a domestic 220kV substation the phenomenon of exceeding the limits and the noise tax should be paid , Also studied the available noise reduction measures , It provides reference for planning and noise control of 220kV substation in the future.
Key words: Environmental protection law of the peoples Republic of China;Noise tax ;Noise abatement
即將于2018年1月1日起实施的《中华人民共和国环境保护税法》正式将噪声纳入到应税污染物的范围中,这也意味着过去按照《排污费征收标准管理办法》征收的噪声超标排污费将退出历史舞台[1]。2016年,全国各级环保部门共收到环境噪声投诉52.2万件,办结率为99.1 %。其中,工业噪声类占10.3 %,建筑施工噪声类占50.1 %,社会生活噪声类占36.6 %,交通运输噪声类占3.0 %[2]。由此看见,环境噪声投诉量占环境投诉总量的43.9%,已成为公众反映强烈的环境问题之一,而征收噪声税也成为治理噪声污染的一个重要手段。
1 环境保护税法关于噪声的税额标准
根据《中华人民共和国环境保护税法》的规定,工业噪声税额是按照超标分贝值来计算,共划分为6个等级:超标1~3分贝,每月税额为350元;超标4~6分贝,每月税额为700元;超标7~9分贝,每月税额为1400元;超标10~12分贝,每月税额为2100元;超标10~12分贝,每月税额为2800元;超标13~15分贝,每月税额为5600元;超标16分贝以上,每月税额为11200元,具体征税要求见下表。
2 国内某220kV变电站规划及布置
2.1 变电站规划及现状
变电站远期规划建设3台容量180MVA主变压器,全站按220kV、110kV、10kV三级电压设置,220kV规划出线4回;110kV规划出线12回; 10kV规划出线16回。
变电站现已建设2台容量180MVA主变压器 220kV出线2回;110kV出线1回;10kV出线16回。两台主变10kV侧各装设3×8Mvar的电容器。
本期工程建设1台180MVA变压器(3号主变)。
2.2 变电站平面布置情况
变电站平面布置呈刀把形,东西长110.5m,南北宽118.4m,围墙内面积1.245hm2,现状站区围墙高度2.3m。
变电站新建时由于工程建设用地指标紧张,因此总平面布置采用紧凑式布置方案压缩用地指标,使3号主变距离站区西侧围墙最近距离为9.4m,因此本期工程3号主变扩建完成后,导致站区西侧围墙出现噪声超标现象。
3 噪声控制设计方案
3.1 噪声排放执行标准
3.2 噪声影响预测分析
3.2.1 源强分析
本工程扩建工程完成后主要噪声源强为1号主变、2号主变、3号主变,源强情况见下表。
3.2.2 预测方法
预测方法:建立坐标系,确定各声源坐标和预测点坐标,并根据声源性质以及预测点和声源之间的距离等情况,按最不利情况考虑,将变电站3个主变简化为3个体源,只考虑厂界处围墙的隔声作用,计算出噪声从各声源传播到预测点的声衰减量,由此计算出各声源作用在预测点噪声的叠加值。
预测软件:soundplan。
建模情况:按最不利情况,源强按体源考虑。
3.2.3 噪声影响预测
本工程建成后,站内源强增加,厂界只有围墙情况下进行预测计算时预测结果为:本期工程扩建后,变电站厂界本次扩建主变一侧(变电站的西侧)预测值为53dB(A),南侧厂界预测值为48dB(A),北侧厂界预测值为48dB(A),东侧厂界预测值为46dB(A),西侧厂界噪声值超过《工业企业厂界环境噪声排放标准》(GB12348-2008)中2类标准中夜间50dB(A)的要求,最大超标值为3 dB(A),其余厂界均满足标准。
厂界只有围墙隔声情况下噪声预测等值线预测见图2。
3.2.4 噪声超标经济损益分析
变电站若按照原规划建设,则西侧厂界噪声昼间达标,夜间超过《工业企业厂界环境噪声排放标准》(GB12348-2008)中2类标准夜间50dB(A)的要求,夜间最大超标3 dB(A),根据《中华人民共和国环境保护税法》的规定,变电站为连续不间断运行方式,不涉及减半计算应纳税额情况,西侧厂界噪声昼间达标,夜间不达标,因此不累计计征噪声税,按照表1规定,超标1~3分贝,每月纳税额为350元/月,年纳税额为4200元/年,变电站一般设计寿命为40年左右,则设计寿命年内应纳税额为16.8万元。
3.3 噪声治理措施
变电站专项降噪措施分为隔声、消声、吸声和隔振等,根据噪声源具体情况选取适当的降噪措施,对于本工程,降噪措施主要考虑声源控制和隔声措施。
3.3.1 声源控制
本工程只考虑站区围墙的隔声作用时,经模式预测计算,如实现厂界达标,主变压器噪声水平应低于下表中所列数值。
主变压器出厂时,设备制造厂家须完成出厂噪声检测,提供检测报告。报告应包括如下内容:被检测设备的相关参数(型号、尺寸等)、测点分布图、测试时设备所處的工况、测试前后背景噪声情况、被测设备所处的环境(四周距离墙壁等障碍物的距离)、空载噪声测试值、短路噪声测试值、满负荷运行噪声保证值、辐射声功率级。
3.3.2 主变围墙侧增设防火墙
变电站扩建主变后,根据站区内平面布置情况,在扩建3号主变西侧2.34m处增设防火墙一道,新建防火墙长14.44m、高7.5m(与1号、2号现有防火墙长度一致),墙体及墙体表面应采用吸声材料,进一步提高降噪效果。增加防火墙后,建模预测本期扩建主变侧围墙的西侧厂界噪声值为50dB(A),达到《工业企业厂界环境噪声排放标准》(GB12348-2008)中2类标准昼间60dB(A)、夜间50dB(A)要求。
扩建主变围墙侧增设防火墙噪声预测等值线见附图3。
4 结论
本文通过对即将实施的《中华人民共和国环境保护税法》中关于噪声税的征收要求介绍,结合对国内某220kV变电站前期规划未考虑后期扩建工程高噪声设备布置情况,致使厂界噪声出现超标现象及应缴纳噪声税的情况进行了分析,对可采取的降噪措施进行了研究,为今后220kV变电站规划及噪声治理提供了参考依据。
参考文献
[1]尚风科技.环保税即将开征,你知道企业噪声税怎么计算吗?[EB/OL].http://dy.163.com/v2/article/detail/CV229SC40518 MEKF.html.2017-09-23/2017-11-7.
[2]中华人民共和国环境保护部. 中国环境噪声污染防治报告[R].北京:中华人民共和国环境保护部, 2017. 1-1.
[3] GB12348-2008, 工业企业厂界环境噪声排放标准[S].
[4] DL/T1518-2016, 变电站噪声控制技术导则[S].
收稿日期:2017-11-08
作者简介:杜乐(1984-),男,大学本科,工程师,研究方向为火电厂及输变电工程环境影响评价。